Chronicle of Work

13.08.2018

Suburban Branch

13.08.2018

Suburban Branch

11.08.2018

Suburban Branch

10.08.2018

Suburban Branch

10.08.2018

Nizhnekamsky Branch

09.08.2018

Aksubaevsky Branch

06.08.2018

Suburban Branch

06.08.2018

Suburban Branch

03.08.2018

Suburban Branch

03.08.2018

Suburban Branch

30.07.2018

Drozhzhanovsky Branch

Construction of asphalt base course is conducted on site “Reconstruction of the auto road Staroye Drozhzhanoye – Tatarskiye Shatrashany, part 12+800 – km 15+360 in Drozhzhanovsky municipal district of the Republic of Tatarstan".

30.07.2018

Mamadyshsky Branch

Workers of the company conduct laying of macadam-and-mastics asphalt surface course (grade 10) on the auto road “Mamadysh-Kukmor”, part km 18+500 – km 21+040 in Mamadyshsky municipal district of the Republic of Tatarstan.

30.07.2018

Menzelinsky Branch

Construction of the asphalt-concrete base course is finished on site “Reconstruction of the access road to Nizhneye Yashkheyevo village” in Aktanyshsky municipal district of the Republic of Tatarstan.

30.07.2018

Nizhnekamsky Branch

Works successfully finished on site “Reconstruction of the asphalted road network in the inhabited localities of Nizhnekamsky municipal district of the Republic of Tatarstan (auto road on Muradyan street from “Shifaly” bus stop to Lesnaya str.).

30.07.2018

Nizhnekamsky Branch

Workers of the company construct surface course of macadam-and-mastics mix (grade 5) in Blagodatnoye village, Mira street, in accordance with the program “Reconstruction of the asphalted road network in the inhabited localities of Nizhnekamsky municipal district of the Republic of Tatarstan (transition type of surface)".

26.07.2018

Nizhnekamsky Branch

Construction of the surface course (macadam-and-mastics asphalt grade 20) and strengthening of roadsides with macadam (grade 400) are finished on site “Reconstruction of the auto road Zainsk-Sukharevo, part km 28+600 - km 32+600 (2nd stage, km 28+600 - km 31+075) in Nizhnekamsky municipal district of the Republic of Tatarstan».

25.07.2018

Aksubaevsky Branch

Construction of the surface course of macadam-and-mastics mix (grade 10) on the auto road “Chistopol-Aksubayevo-Nurlat”, part km 72+566 – km 74+921 and km 77+776 – 78+569 in Aksubayevsky municipal district of the Republic of Tatarstan.

25.07.2018

Aksubaevsky Branch

Construction of the asphalted surface 5 cm thick of macadam-and-mastics mix grade 20 on the auto road “Kuzaykino-Nurlat, part km 36+550 – km 38+600 in Cheremshansky municipal district of the Republic of Tatarstan.

24.07.2018

Mamadyshsky Branch

Workers of the company conduct soil stabilization works (with addition of lime) on site “Reconstruction of the auto road “Uzyak-Alga-Petrovsky” in Tiulyachinsky municipal district of the Republic of Tatarstan.

24.07.2018

Drozhzhanovsky Branch

Recycling works with addition of cement are finished on site “Reconstruction of the auto road “Staroye Drozhzhanoye – Tatarskiye Shatrashany, part km 12+800 – km 15+360” in Drozhzhanovsky municipal district of the Republic of Tatarstan.

16.07.2018

Aksubaevsky Branch

Construction of base course of asphalt-concrete surface (material used: 7 cm thick porous coarse-grained asphalt-concrete mix, grade M-II) on the auto road “Kuzaikino – Nurlat”, part km 36+550 – km 38+600 in Cheremshansky municipal district of the Republic of Tatarstan.

13.07.2018

Chelninsky Branch

Workers of the company construct upper surface layer of macadam-and-mastics asphalt grade 10 on site “Reconstruction of Vakhitov ave. from Chulman ave. to Suumbike ave., Naberezhnye Chelny city”.

13.07.2018

Apastovsky Branch

Construction of road bed using cold recycling method with addition of mineral aggregate (M-800 macadam grade 20-70 mm) on site “Reconstruction of the auto road “Tetiushi-Kamskoye Ustye”, part km 24+140 – km 26+900 in Kamsko-Ustyinsky district of the Republic of Tatarstan.

12.07.2018

Apastovsky Branch

Workers of the company construct bottom layer of porous coarse-grained asphaltic surface and strengthen the slopes on site “Reconstruction of the auto road Biurgany – settlement of Burunduki railroad station in Buinsky municipal district of the Republic of Tatarstan (1st stage)”.

12.07.2018

Apastovsky Branch

Reconstruction of worn-out layers of asphalt is conducted on the auto road “Bolshiye Kaibitsy – Kamylovo”, part km 1+905 – km 3+065 in Kaibitsky municipal district of the Republic of Tatarstan.

12.07.2018

Drozhzhanovsky Branch

Workers of the company conduct construction of road bed using cold recycling method with addition of mineral aggregate (M-800 macadam grade 20-70 mm) on site “Reconstruction of the auto road “Staroye Drozhzhanoye – Tatarskiye Shatrashany”, part km 12+800 – km 15+360 in Drozhzhanovsky municipal district of the Republic of Tatarstan.

12.07.2018

Apastovsky Branch

Workers of the company conduct summer road maintenance works on the federal and regional public auto roads in Buinsky, Verkhneuslonsky and Kaibitsky municipal districts of the Republic of Tatarstan.

12.07.2018

Apastovsky Branch

Workers of the company continue surfacing works on site “Reconstruction of the auto road Biurgany - settlement of Burunduki railway station in Buinsky municipal district of the Republic of Tatarstan (stage1)”.

12.07.2018

Apastovsky Branch

Improvements on the production base of Kamsko-Ustyinsky maintenance depot of Apastovsky branch of JSC “Tatatvtodor”: asphalted surface course was constructed.

11.07.2018

Apastovsky Branch

Workers of Apastovsky branch of JSC “Tatavtodor” have started milling of asphalted surface on site “Auto road Ulanovo-Karatun, part km 2+293 - km 4+493 in Verkhneuslonsky municipal district of the Republic of Tatarstan (reconstruction of worn-out surfaces)".

10.07.2018

Menzelinsky Branch

Site “Construction of the auto road “M-7 “Volga” – Noviy Melken” – Dusai-Kichu in Menzelinsky municipal district of the Republic of Tatarstan". Stabilization of subgrade soil with lime.

07.07.2018

Menzelinsky Branch

Site “Reconstruction of the auto road “M-7 “Volga” – Noviy Melken in Menzelinsky municipal district of the Republic of Tatarstan". Construction of the asphalt-concrete surface course.

04.07.2018

Suburban Branch

Construction of base course of porous coarse-grained asphalt-concrete mix on site “Reconstruction of the auto road Sokury-Kirbi-Travkino, part km 5+000 – km 6+000 in Laishevsky municipal district of the Republic of Tatarstan".

04.07.2018

Suburban Branch

Construction of surface course of macadam-and-sand mix on site “Construction of Access road to Bolshoy Pochinok village in Vysokogorsky municipal district of the Republic of Tatarstan".

04.07.2018

Nizhnekamsky Branch

Workers of the company conduct construction of the road upper layer of dense asphalt-concrete mix type B on site “Access road to non-commercial allotment gardens “Veteran”, “Sputnik”, “Energetik-1”, allotments “Kama-2”, “Kama”, “Teploenergostroy”, “Stroitel”, “City non-commercial allotment of Nizhnekamsk”, gardening cooperative “Sadovod-NK”, gardening consumer’s cooperatives “Neftekhimik”, “Shinnik” in Nizhnekamsky municipal district of the Republic of Tatarstan”.

02.07.2018

Drozhzhanovsky Branch

Construction of asphalt bedding course is conducted on site “Reconstruction of the auto road “Kazan-Ulyanovsk” – Staroye Drozhzhanoye, part km 7+000 – km 9+248” in Drozhzhanovsky municipal district of the Republic of Tatarstan.

29.06.2018

Suburban Branch

Construction of leveling course, milling of asphalt-concrete surface on site “Reconstruction of the auto road Kazan-Malmyzh, part km 19+320 – km 21+920 in Vysokogorsky municipal district of the Republic of Tatarstan".

29.06.2018

Suburban Branch

Construction of macadam-and-sand mix (grade 10) surface course on the auto road Stolbistche-Atabayevo, part km 6+000 – km 9+000 in Laishevsky municipal district of the Republic of Tatarstan.

29.06.2018

Suburban Branch

Construction of surface course and strengthening of slopes with macadam on the auto road “M-7 “Volga” – Kulayevo-Pestretsy, part km 0+000 – km 1+600 and km 2+100 – km 4+346 in Pestrechinsky municipal district of the Republic of Tatarstan.

29.06.2018

Nizhnekamsky Branch

Construction of surface course of asphalt-concrete (macadam-and-mastics, grade 10) jn site “Reconstruction of the asphalted road network in the inhabited localities of Nizhnekamsky municipal district of the Republic of Tatarstan (reconstruction of the auto road on Muradyan street from “Shifaly” bus stop to Krasniy Kliuch settlement).

29.06.2018

Mamadyshsky Branch

Construction of the earth bed on site “Reconstruction of the auto ro ad “Uzyak-Alga_Petrovsky” in Tiulyachinsky municipal district of the Republic of Tatarstan".

29.06.2018

Nizhnekamsky Branch

Workers of the company conduct construction of the racking course of porous asphalt-concrete mix on site “Access road to non-commercial allotment gardens “Veteran”, “Sputnik”, “Energetik-1”, allotments “Kama-2”, “Kama”, “Teploenergostroy”, “Stroitel”, “City non-commercial allotment of Nizhnekamsk”, gardening cooperative “Sadovod-NK”, gardening consumer’s cooperatives “Neftekhimik”, “Shinnik” in Nizhnekamsky municipal district of the Republic of Tatarstan”.

29.06.2018

Drozhzhanovsky Branch

Road bed construction works using cold recycling method with addition of aggregate are finished on site: “Reconstruction of the auto road “Kazan-Ulyanovsk” – Staroye Drozhzhanoye, part km 0+442 – km 2+353” in Buinsky municipal district of the Republic of Tatarstan.

29.06.2018

Drozhzhanovsky Branch

Recycling works (with addition of binding and soil stabilization with lime) are finished on site: “Reconstruction of the auto road “Kazan-Ulyanovsk” – Staroye Drozhzhanoye, part km 7+000 – km 9+248” in Drozhzhanovsky municipal district of the Republic of Tatarstan.

29.06.2018

Nizhnekamsky Branch

Workers of the company are mowing the grass off the auto roads in Nizhnekamsky municipal district of the Republic of Tatarstan.

29.06.2018

Аrsky Branch

Summer season auto road maintenance works in Arsky municipal district of the Republic of Tatarstan.

27.06.2018

Aksubaevsky Branch

Workers of the company conduct construction of the upper surface layer made of macadam-and-mastics asphalt (grade 20) on the auto road Kuzaykino-Nurlat (part km 22+725 – km 24+420, stage 2) in Cheremshansky municipal district of the Republic of Tatarstan.

25.06.2018

Menzelinsky Branch

Works on site “Reconstruction of the auto road M-7 “Volga” – Staroye Aymanovo – Oktyabr, part Tatarskoye Bulyarovo-Urazmetyevo, in Musliumovsky municipal district of the Republic of Tatarstan". Workers of the company construct bedding course of the asphalt-concrete surface and foundation pit for the pipe.

21.06.2018

Suburban Branch

Site “Construction of the auto road Access to Bolshoy Pochinok village in Vysokogorsky municipal district of the Republic of Tatarstan". Stabilization and strengthening of the soil on site with lime.

21.06.2018

Drozhzhanovsky Branch

Reconstruction of the road network in Alyoshkin Saplyk inhabited locality in Drozhzhanovsky municipal district of the Republic of Tatarstan have been successfully finished.

20.06.2018

Nizhnekamsky Branch

In accordance with the program “Reconstruction of the road network in the inhabited localities of Nizhnekamsky municipal district of the Republic of Tatarstan", workers of the company conduct construction of asphalt-concrete mix surface (type B-2) bedding in Blagodatnoye village (Mir street).

20.06.2018

Suburban Branch

Construction of the road bed on the auto road Rybnaya Sloboda-Yanchikovo is conducted in Rybno-Slobodsky municipal district of the Republic of Tatarstan.

20.06.2018

Drozhzhanovsky Branch

Workers of the company conduct bedding construction using cold recycling method with addition of aggregate on site “Reconstruction of the auto road “Kazan-Ulyanovsk”-Staroye Drozhzhanoye, part km 7+000 – km 9+248 in Drozhzhanovsky municipal district of the Republic of Tatarstan.

19.06.2018

Chelninsky Branch

Reconstruction of the asphalt-concrete surface at Vakhitov avenue in Naberezhnye Chelny city.

19.06.2018

Suburban Branch

Improvement of the territory of production base of Suburban branch, Usady settlement, Laishevsky municipal district of the Republic of Tatarstan. Construction of leveling and surface courses.

19.06.2018

Suburban Branch

Construction of dense asphalt-concrete mix (type B, grade 2) leveling course on the auto road Stolbistche-Atabayevo, part km 6+000 – km 9+000 in Laishevsky municipal district of the Republic of Tatarstan.

19.06.2018

Suburban Branch

Milling of the asphalted surface on the auto road Kazan-Malmyzh, part km 19+320 – km 21+920 in Vysokogorsky municipal district of the Republic of Tatarstan.

19.06.2018

Suburban Branch

Workers of the company mow the grass off with tractor-mounted mowing machines and trimmers.

19.06.2018

Apastovsky Branch

Construction of mass concrete foundation for the shell of reinforced concrete pipe on site “Reconstruction of the auto road Tetiushi-Kamskoye Ustye, km 2+300 – km 11+800 (stage IV: km 9+855 – km 11+843) in Tetiushsky municipal district of the Republic of Tatarstan”.

08.06.2018

Suburban Branch

Our workers continue construction of the road bed on site “Construction of the auto road Access to Bolshoy Pochinok village in Vysokogorsky municipal district of the Republic of Tatarstan”.

08.06.2018

Suburban Branch

On photo: milling of the asphalt-concrete surface on the auto road Stolbistche-Atabayevo, part km 6+000 – km 9+000 in Laishevsky municipal district of the Republic of Tatarstan”.

08.06.2018

Nizhnekamsky Branch

Final stage of construction works on site “Reconstruction of the asphalted road network in the inhabited localities of Nizhnekamsky municipal district of the Republic of Tatarstan“ (auto road to the City hall of records, Akhtubinskaya street 6B).

08.06.2018

Menzelinsky Branch

On photo: site “Reconstruction of the auto road M-7 “Volga” – Staroye Aymanovo – Oktyabr, part Tatarskoye Bulyarovo – Urazmetyevo in Musliumovsky municipal district of the Republic of Tatarstan“. Workers of the company conduct construction of cement-bound macadam-and-sand road bed.

01.06.2018

Menzelinsky Branch

Workers of the company construct upper layer of the road surface on site “Reconstruction of the asphalted road network of the inhabited localities in Aktanyshsky municipal district of the Republic of Tatarstan“.

01.06.2018

Nizhnekamsky Branch

Workers of the company construct auto road base course of solid asphalt-concrete (B2 type) on site “Reconstruction of the asphalted road network in inhabited localities of Nizhnekamsky municipal district of the Republic of Tatarstan (reconstruction of the auto road at Muradyan street from “Shifaly” bus stop to Krasniy Kliuch settlement)”.

31.05.2018

Suburban Branch

Clean-up after the windstorm of May 30, 2018 in Laishevsky municipal district of the Republic of Tatarstan.

31.05.2018

Suburban Branch

Workers of the company conduct earth bed construction works on site “Construction of the auto road Access road to Bolshoy Pochinok village in Vysokogorsky municipal district of the Republic of Tatarstan.

30.05.2018

Sabinsky Branch

Reconstruction of worn-out asphalt-concrete surfaces is conducted on the auto road “Bypass of Bogatye Saby settlement” using the funds provided for road maintenance in Sabinsky municipal district of the Republic of Tatarstan.

29.05.2018

Mamadyshsky Branch

Workers of the company conduct road works on site “Reconstruction of asphalted road network in inhabited localities of Mamadyshsky municipal district of the Republic of Tatarstan”.

28.05.2018

Аrsky Branch

Workers of Arsky branch of the company had started construction of the asphalt-concrete surface on site “Reconstruction of the road network in the inhabited localities of Arsky municipal district of the Republic of Tatarstan”.

25.05.2018

Menzelinsky Branch

Reconstruction of worn-out asphalt-concrete surfaces is conducted on the auto road “Bypass Menzelinsk city” using the funds provided for road maintenance in Menzelinsky municipal district of the Republic of Tatarstan.

24.05.2018

Apastovsky Branch

Workers of the company conduct summer maintenance works on the auto roads in Verkhneuslonsky, Kaibitsky and Tetiushsky municipal districts of the Republic of Tatarstan.

24.05.2018

Suburban Branch

Summer maintenance works on the regional and federal public auto roads in Vysokogorsky, Pestrechinsky and Laishevsky municipal districts of the Republic of Tatarstan.

23.05.2018

Apastovsky Branch

Workers of the company conduct construction of the upper layer made of asphalt-concrete mix (grade 10) on site “Reconstruction of the auto road M-7 “Volga” – Vvedenskaya Sloboda, part km 0+000 – km 3+500 in Verkhneuslonsky municipal district of the Republic of Tatarstan”.

18.05.2018

Suburban Branch

Workers of the company conduct construction of the leveling course made of porous fine-grained asphalt-concrete mix (grade 2) on site “Reconstruction of the auto road Rybnaya Sloboda – Yanchikovo in Rybno-Slobodsky municipal district of the Republic of Tatarstan (stage 2)”.

08.05.2018

Apastovsky Branch

Workers of the company conduct bedding construction works using cold recycling method with addition of mineral aggregate and construction of compact coarse-grained mix (type BM II) base course on site “Reconstruction of the auto road M-7 Volga – Vvedenskaya Sloboda, km 0+000 – km 3+500” in Verkhneuslonsky municipal district of the Republic of Tatarstan.