August - September 2013

21.09.2013

Аrsky Branch

After ground works recultivation of allocated part of earth side cutting is done on site “Reconstruction of the auto road Kutuk – Kazanbash in Arsky district of the Republic of Tatarstan”.

20.09.2013

Chelninsky Branch

Slopes are being stabilized on site “Construction of the auto road “Buraly-Rantamak”-Aleksandrovka”-Almetiyevsk-Musliumovo”-Tatarskiye Karamaly” in Sarmanovsky district of the Republic of Tatarstan.

20.09.2013

Menzelinsky Branch

Asphalt bedding course is being laid on site “M-7 Volga” – Noviy Melken” in Menzelinsky district of the Republic of Tatarstan.

18.09.2013

Menzelinsky Branch

Site “Reconstruction of the auto road “Verkhniy Tabyn - Togashevo” in Musliumovsky district of the Republic of Tatarstan. Here, sand-and-gravel mix bottom course is being constructed using mix-in-place method and roadbed slopes are being leveled.

17.09.2013

Sabinsky Branch

Construction of the auto road “Verkhniy Iskubash – Nizhniy Iskubash” – Bitlyangur in Kukmorsky district of the Republic of Tatarstan is finished.

13.09.2013

Menzelinsky Branch

Site “Reconstruction of the auto road “Verkhniy Tabyn - Togashevo” in Musliumovsky district of the Republic of Tatarstan. Here, sand-and-gravel mix is being delivered and prepared for construction of bottom course using mix-in-place method.

13.09.2013

Mamadyshsky Branch

The construction of pavements, protective works on conduit pipes and mounting of guard rails are being finished on site “Reconstruction of the auto road “Ishkeyevo – Nizhniy Takanysh” – Chaksy.

13.09.2013

Mamadyshsky Branch

Construction of the road bed and asphalt course is finished on site “Reconstruction of the auto road “Kemesh-Kul – Algayevo” in Mamadyshsky district of the Republic of Tatarstan.

13.09.2013

Аrsky Branch

Construction of sand-and-gravel mix bottom course and macadam road bed is finished on site “Reconstruction of the auto road Kazan-Shemordan, km 63+504 – km 65+434 in Tulyachinsky district of the Republic of Tatarstan. Asphalt bedding course is being laid.

11.09.2013

Menzelinsky Branch

Site “M-7 Volga” – Noviy Melken” in Menzelinsky district of the Republic of Tatarstan. Here, bottom course is being constructed using mix-in-place method, stabilized with sand-and-gravel mix and cement.

10.09.2013

Аrsky Branch

Asphalt-concrete is being laid on site “Reconstruction of the auto road Pechmentau-Stariy Kiner in Arsky district of the Republic of Tatarstan.

04.09.2013

Menzelinsky Branch

Asphalt-concrete surface course is being laid on site “Construction of the auto road “Almetiyevsk- Musliumovo” – Igenche” in Musliumovsky district of the Republic of Tatarstan.

03.09.2013

Menzelinsky Branch

Ground course is being stabilized with lime on site “Reconstruction of the auto road “Verkhniy Tabyn - Togashevo” in Musliumovsky district of the Republic of Tatarstan.

01.09.2013

Аrsky Branch

Roadsides are being stabilized with M-400 macadam on site “Reconstruction of the auto road Pimeri – Yunusovo in Pestrechinsky district of the Republic of Tatarstan”.

29.08.2013

Suburban Branch

Racking course of porous fine-graded bituminous concrete is being laid on site “Reconstruction of the auto road “Kazan-Orenburg” – Rybnaya Sloboda – Kornoukhovo” – Bolshoy Oshnyak – Malyi Oshnyak in Rybno-Slobodsky district of the Republic of Tatarstan”.

28.08.2013

Chelninsky Branch

Sandy subsoil with geogrid above is being laid on site “Construction of the auto road “M-7 “Volga” – Kutlu -Bukash – Rybnaya Sloboda – Bikchurayevo in Rybno-Slobodsky district of the Republic of Tatarstan”.

28.08.2013

Chelninsky Branch

Reinforced concrete pipe is being mounted on site “Construction of the auto road “Buraly-Rantamak” – Aleksandrovka” – Almetiyevsk – Musliumovo” – Tatarskiye Karamaly” in Sarmanovsky district of the Republic of Tatarstan”.

28.08.2013

Sabinsky Branch

Reconstruction of the auto road “Kazan – Shemordan”, km 90+400 – km 98+607 in Sabinsky district of the Republic of Tatarstan. Single-coat asphalt course 6 cm thick of dense asphalt-concrete mix type Б and М-2 was laid on part “Drive to school” 0.640 km long.

28.08.2013

Sabinsky Branch

Construction of the auto road “Kukmor – Shemordan”-Nyriya-Ishtugan”- Baldy Knya in Kukmorsky district of the Republic of Tatarstan. Base course 0.18 m thick 0.995 km long of M-800 macadam is being made here.

28.08.2013

Suburban Branch

Subsoil with geogrid above and base course are being laid on site “Construction of the auto road “Peschyaniye Kovali – Orlovka” – Tarlashi in Laishevsky district of the Republic of Tatarstan”.

24.08.2013

Mamadyshsky Branch

Sowing and land recultivation of easement areas on site “Construction of the auto road “Ishkeyevo – Nizhniy Takanysh – Chaksy ”, km 1+500 – km 6+200 in Mamadyshsky district of the Republic of Tatarstan”.

24.08.2013

Drozhzhanovsky Branch

Earth excavations are being made on site “Reconstruction of the auto road “Ulanovo – Karatun” – Kaby Kopri, part Utiyamishevo – Kaby Kopri in Apastovsky district of the Republic of Tatarstan”.

24.08.2013

Apastovsky Branch

Reconstruction of the auto road “Kazan – Uliyanovsk” – Staroye Baryshevo – Kamskoye Ustiye” – Yasashno- Baryshevo in Apastovsky district of the Republic of Tatarstan is finished.

24.08.2013

Apastovsky Branch

Reconstruction of the auto road “Normalization of the road net in settlement Maliye Bolgoyary” in Apastovsky district of the Republic of Tatarstan is finished.

23.08.2013

Apastovsky Branch

Construction of the auto road “Drive to village Labyshka” in Kamsko-Ustiynsky district of the Republic of Tatarstan is finished.

23.08.2013

Apastovsky Branch

Reconstruction of the auto road “Kazan-Uliyanovsk” – Staroye Baryshevo – Kamskoye Ustiye” Almenderovo - Maliye Bolgoyary”, km 0+000 – km 4+230 in Apastovsky district of the Republic of Tatarstan is finished.

22.08.2013

Menzelinsky Branch

ЩМА – 15 macadam and mastics wearing course was laid on site “M-7 “Volga” – Stariy Irkenyash – Tatarskaya Mushuga” in Menzelinsky district of the Republic of Tatarstan”.

22.08.2013

Mamadyshsky Branch

Macadam road bed and base and wearing courses are being constructed on the auto road “Usali-Albay-Vladimirovo”.

21.08.2013

Suburban Branch

Base course of porous coarse grain asphalt concrete is being constructed on site “Construction of the auto road Obukhovo-Tagashevo in Laishevsky and Pestrechinsky districts of the Republic of Tatarstan”.

21.08.2013

Menzelinsky Branch

Construction of asphalt concrete base course is almost finished on site “Tiukovo – Tatarskiye Yamaly”, km 17+550 – km 21+000 in Aktanyshsky district of the Republic of Tatarstan”.

21.08.2013

Menzelinsky Branch

Topsoil stripping and constructional works are being made on site “Verkhniy Tabyn – Togashevo” in Musliumovsky district of the Republic of Tatarstan”.

21.08.2013

Menzelinsky Branch

Road subsoil and concrete pipe foundation are being constructed on site “Almetiyevsk – Musliumovo” – Igenche” in Musliumovsky district of the Republic of Tatarstan”.

21.08.2013

Mamadyshsky Branch

Double-coat asphalt concrete coating was laid on the bridge across Shumbutka river on km 917 of auto road M-7 “Volga”.

21.08.2013

Mamadyshsky Branch

Earth roadbed is being constructed on site “Reconstruction of the auto road Kemesh-Kul – Algayevo in Mamadyshsky district of the Republic of Tatarstan”.

21.08.2013

Nizhnekamsky Branch

Reconstruction of auto roads in Nizhnekamsk.

14.08.2013

Аrsky Branch

On site “Reconstruction of the auto road “Kazan-Shemordan-Yambulat km 0+00 – km 2+00 in Tulyachinsky district of the Republic of Tatarstan” the lower road structure is being constructed using “mix-in-place” cold regeneration method with addition of cement and bitumen emulsion to the enriched sand and gravel mix.

05.08.2013

Аrsky Branch

On site “Reconstruction of the auto road “Arsk-Tulyachi” – Bolshoy Shinar in Sabinsky district of the Republic of Tatarstan” the ground works are being finished, the lower road structure is being constructed on km 0+00 – km 13+70, and asphalt bedding course is being laid.

02.08.2013

Menzelinsky Branch

Reconstruction of the auto road “M-7 Volga – Novy Melken”in Menzelinsky district of the Republic of Tatarstan. Here, water pipe conduit is being constructed.

02.08.2013

Menzelinsky Branch

On site “Reconstruction of the auto road “Tiukovo – Tatarskiye Yamaly” km 17+550 – km 21+000 in Aktanyshsky district of the Republic of Tatarstan” the lower road structure is being constructed using “mix-in-place” method of stabilization with sand and gravel mix and cement.