May - October 202310/30/2023 Аrsky Branch "Arsk – Bolshaya Atnya" - Koshlauch: 0+000 - 4+431 (Arsky district)
Construction of roadsides strengthened with M-400 macadam. 10/26/2023 Aksubaevsky Branch Road network (macadam-and-sand mix) 2023 (Aksubayevsky district): 0+000 - 0+220; 0+000 - 0+165; 0+000 - 0+113; 0+000 - 0+259; 0+000 - 0+735 (Aksubayevsky district)
Workers of JSC “Tatavtodor” have finished reconstruction works in Aksubayevo (Within road reconstruction program). 10/23/2023 Аrsky Branch "Arsk – Bolshaya Atnya" - Koshlauch: 0+000 - 4+431 (Arsky district)
Construction of top coat with porous asphaltic mix (grade 8) 0.04 m thick. 10/20/2023 Аrsky Branch M-7 "Volga” – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Strengthening of roadsides with M-400 macadam, layer thickness 0.12 m. 10/19/2023 Аrsky Branch “Kazan – Shemordan” – Lesnoy: 9+090 - 13+275 (Tiulyachinsky district)
Construction of top coat with stone mastics mix (grade 5) 0.02 m thick. 10/17/2023 Menzelinsky Branch "M-7 “Volga” – Konovalovka” – Staraya Ashpala: 0+000 - 2+860 (Menzelinsky district)
Construction of top coat with stone mastics mix (grade 8) and sideways is finished. 10/16/2023 Аrsky Branch "Arsk – Bolshaya Atnya" - Koshlauch: 0+000 - 4+431 (Arsky district)
Construction of asphaltic base course with А32Нн asphalt-concrete 0.07 m thick. 10/16/2023 Аrsky Branch M-7 "Volga” – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Construction of top coat with stone mastics mix (grade 8). 10/16/2023 Аrsky Branch “Kazan – Shemordan” – Lesnoy (Tiulyachinsky district)
Construction of asphaltic surface course. 10/15/2023 Аrsky Branch “Kazan – Shemordan” – Lesnoy: 9+090 - 13+275 (Tiulyachinsky district)
Construction of asphaltic base course. 10/14/2023 Nizhnekamsky Branch Vakhitova Avenue (from Sobolekovskaya Street to the Khimikov Avenue-Vakhitov Avenue roundabout): 0+000 - 1+465 (Nizhnekamsky district)
Works are finished. 10/13/2023 Suburban Branch Airport – Stolbische: 0+107 – 3+405 (Laishevsky district)
Strengthening of roadsides with asphalt-concrete granulate. 10/13/2023 Menzelinsky Branch "Aktanysh – Poisevo" – Bulyak: 9+920 - 16+020 (Aktanyshsky district)
Works are finished. 10/12/2023 Suburban Branch Kazan – Shemordan: 31+146 - 33+440 (Pestrechinsky district)
Construction of leveling course with А16Нт asphalt-concrete mix. Construction of stone mastics (grade 8) surface course. 10/10/2023 Mamadyshsky Branch "M-7 "Volga" – Sekines" – Omary: 0+000 - 3+822 (Mamadyshsky district)
Works are finished. 10/09/2023 Buinsky Branch "Staroye Drozhzhanoye – Tatarskiye Shatrashany" – Gorodische (Drozhzhanovsky district)
Works are finished. 10/05/2023 Аrsky Branch Kazan- Shemordan: 68+750 - 70+088 (Tiulyachinsky district) 10/04/2023 Аrsky Branch
Kazan – Shemordan: 65+575 - 67+624 (Tiulyachinsky district) 10/04/2023 Аrsky Branch
Kazan – Shemordan: 67+624 - 68+750; 64+975 - 65+575 (Tiulyachinsky district) 10/04/2023 Аrsky Branch Kazan – Shemordan: 78+700 - 81+678 (Tiulyachinsky district)
Works are finished. 10/04/2023 Suburban Branch Airport – Stolbische: 0+107 – 3+406 (Laishevsky district)
Cold milling of asphaltic surface.
Construction of leveling course using А16Нт asphalt-concrete mix.
Construction of stone mastics (grade 8) surface course. 09/30/2023 Mamadyshsky Branch Mamadysh – Tiulyachi: 35+800 - 41+825 (Mamadyshsky district)
Works are finished. 09/30/2023 Buinsky Branch Asphalted road network (Drozhzhanovsky district) in 2023: 0+000 - 0+160; 0+000 - 0+270; 0+000 - 0+033; 0+000 - 0+2932 (Drozhzhanovsky district)
Workers of our company conduct construction of 4 cm thick stone mastics (grade 8) surface course. 09/29/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: 0+043 - 2+489 (Arsky district)
Works are finished. 09/27/2023 Menzelinsky Branch M7 "Volga" – Novaya Aleksandrovka – Tulubayevo: 13+460 - 15+710 (Menzelinsky district)
Works are finished. 09/22/2023 Aksubaevsky Branch "Aksubayevo – Yemelkino" – Stary Chuvashsky Adam: 0+000 - 1+440 (Aksubayevsky district)
Workers of the company conduct strengthening of roadsides. 09/22/2023 Aksubaevsky Branch Asphalted road network (Aksubayevsky district) in 2023: 0+000 - 0+299; 0+000 - 0+344 (Aksubayevsky district)
Construction of surface course with stone mastics (grade 5) and RAU-5. 09/22/2023 Buinsky Branch Russkiye Kischaky – Koshki-Novotimbayevo: 0+000 - 2+353 (Tetiushsky district)
Works are finished. 09/21/2023 Menzelinsky Branch "M-7 "Volga" – Konovalovka – Staraya Ashpala: 0+000 - 2+860 (Menzelinsky district) Workers of our company conduct construction of А32Нн base course and leveling course using coated chipping. 09/21/2023 Suburban Branch "Kazan – Orenburg" – Settlement of 25 Oktyabrya collective farm – Aleksandrovsky: 0+000 - 5+453 (Laishevsky district)
Construction of stone mastics (grade 8) surface course. Strengthening of roadsides with M-400 macadam. 09/20/2023 Suburban Branch "Kazan – Orenburg" – Rybnaya Sloboda – Kornoukhovo: 0+000 - 10+880 (Rybno-Slobodsky district)
Construction of turnoff: Workers of our company spread Dornit-300 geotextile and construct C-4 macadam-and-sand base course and surface course of А16Вл asphaltic mix. 09/20/2023 Suburban Branch Stolbische – Atabayevo: 30+550 - 34+550 (Laishevsky district)
Construction of stone mastics (grade 8) surface course. 09/20/2023 Suburban Branch Kamenka – Dubyazy – Bolshaya Atnya: 15+800 - 16+800; 23+990 - 25+999 (Vysokogorsky district)
Cold milling of asphalted surface. Construction of leveling course with А16Нн asphalt-concrete mix. 09/19/2023 Аrsky Branch Kamenka – Dubyazy – Bolshaya Atnya: 41+585 - 42+385 (Atninsky district)
Works are finished. 09/19/2023 Аrsky Branch Kamenka – Dubyazy – Bolshaya Atnya: 42+385 - 43+079 (Atninsky district)
Works are finished. 09/18/2023 Аrsky Branch Arsk – Mari El Republic limits: 1+488 - 4+107 (Arsky district)
Works are finished. 09/18/2023 Buinsky Branch Volniy Stan – Kiyat – Yashevka: 13+300 - 14+990; 30+268 - 31+225 (Buinsky district)
Workers of our company conduct construction of 4 cm thick surface course of stone mastics (grade 8). 09/18/2023 Аrsky Branch "Arsk – Bolshaya Atnya" – Koshlauch: 0+000 - 4+431 (Arsky district)
Construction of additional sandy layer of base course 0.20 m thick. 09/18/2023 Suburban Branch "Rybnaya Sloboda – Yanchikovo" – Maliy Atmas: 0+000 - 3+733 (Rybno-Slobodsky district)
Strengthening of roadsides with M-400 macadam. 09/17/2023 Аrsky Branch Arsk – Mari El Republic limits: 0+000 - 1+488; 4+107 - 6+267 (Arsky district)
Works are finished. 09/16/2023 Buinsky Branch Russkiye Kischaky – Koshki-Novotimbayevo: 0+000 - 3+874 (Buinsky district)
Workers of our company sow the grass and form the roadsides. 09/16/2023 Aksubaevsky Branch "Aksubayevo – Yemelkino" – Stary Chuvashsky Adam: 0+000 - 1+440 (Aksubayevsky district)
Construction of sub-base and top layers. 09/16/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: 0+043 - 2+489 (Arsky district)
Workers of our company conduct construction of stone mastics (grade 8) 4 cm thick surface course. 09/16/2023 Аrsky Branch Kazan – Shemordan: 78+700 - 81+678 (Tiulyachinsky district)
Strengthening of roadsides. 09/16/2023 Аrsky Branch Kazan – Shemordan: 67+624 - 68+750; 64+975 - 65+575 (Tiulyachinsky district)
Strengthening of roadsides. 09/15/2023 Nizhnekamsky Branch Vokzalnaya Street (from Vokzalnaya circle – Korabelnaya Street to Vokzalnaya circle-Stroiteley Avenue): 0+000 - 0+730 (Nizhnekamsky district)
Construction works are finished. 09/14/2023 Nizhnekamsky Branch Chistopol – Nizhnekamsk: 61+173 - 65+656 (Nizhnekamsky district)
Construction works are finished. 09/14/2023 Nizhnekamsky Branch Road network (asphalt-concrete) of Nizhnekamsky district, 2023: 0+000 - 0+610; 0+000 - 0+470 (Nizhnekamsky district)
Construction of stone mastics (grade 16) surface course. 09/14/2023 Menzelinsky Branch "Naberezhnye Chelny – Vodozabor" – Ilbukhtino- Kalmiya – "Menzelinsk – Biyurgan": 6+600 - 9+100 (Tukayevsky district)
Construction works are finished. 09/13/2023 Menzelinsky Branch M-7 "Volga" – Novaya Aleksandrovka – Tulubayevo: 13+460 - 15+710 (Menzelinsky district)
Construction of stone mastics (grade 8) surface course is finished. 09/12/2023 Menzelinsky Branch "M-7 "Volga" – Konovalovka" – Staraya Ashpala: 0+000 - 2+860 (Menzelinsky district)
Workers of our company conduct stabilization of soil with lime using regenerator-mixer, construction of additional bedding layer of sand-and-gravel mix and strengthening of base course with cement using mix-in-place method. 09/11/2023 Menzelinsky Branch "Menzelinsk – Russkiy Karan – Togashevo" – Kuzembetyevo: 3+230 - 5+080 (Menzelinsky district)
Strengthening of roadsides with M-400 macadam. 09/11/2023 Menzelinsky Branch "Aktanysh – Poisevo" – Bulyak: 9+920 - 16+020 (Aktanyshsky district)
Construction of stone mastics (grade 8) surface course on main road and А16Вн mix surface course on exit roads is finished. 09/11/2023 Menzelinsky Branch Aktanysh – Musliumovo: 46+530 - 48+380 (Musliumovsky district)
Construction works are finished. 09/08/2023 Aksubaevsky Branch Chistopol – Aksubayevo – Nurlat: 41+650 - 46+075 (Aksubayevsky district)
Construction works are finished. 09/07/2023 Aksubaevsky Branch Chistopol – Aksubayevo – Nurlat: 75+807 - 77+957 (Aksubayevsky district)
Construction of stone mastics (grade 8) surface course. 09/06/2023 Suburban Branch Usady – Khokhlovo: 0+000 - 5+030 (Vysokogorsky district)
Construction of leveling course using А16Нн asphalt-concrete mix. 09/05/2023 Nizhnekamsky Branch Vakhitova Avenue (from Sobolekovskaya Street to Khimikov Avenue circle – Vakhiova Avenue): 0+000 - 1+465 (Nizhnekamsky district)
Construction of stone mastics (grade 16) surface course. 09/04/2023 Mamadyshsky Branch "M-7 "Volga" – Sekines" – Omary: 0+000 - 3+822 (Mamadyshsky district)
Construction of stone mastics (grade 8) surface course. 09/04/2023 Suburban Branch "Rybnaya Sloboda – Yanchikovo" – Malyi Atmas: 0+000 - 3+733 (Rybno-Slobodsky district)
Construction of stone mastics (grade 8) surface course. 09/04/2023 Mamadyshsky Branch M-7 "Volga" – Sekines, part Ragozino – Omarsky Pochinok: 0+000 - 3+085 (Mamadyshsky district)
Strengthening of roadsides with M-400 macadam. 08/31/2023 Suburban Branch Kazan – Shemordan: 21+977 - 22+777 (Pestrechinsky district)
Stabilization of soil with lime. 08/31/2023 Mamadyshsky Branch M-7 "Volga" (Federal auto roads)
Cleaning of cracks on the road surface. 08/31/2023 Suburban Branch Stolbische – Atabayevo: 30+550 - 34+550 (Laishevsky district)
Construction of А32Нн asphaltic mix binder course. 08/28/2023 Аrsky Branch Bolshaya Atnya – Chepchugy: 0+483 - 0+603 (Atninsky district)
Construction works are finished. 08/28/2023 Suburban Branch "Kazan – Orenburg" – Rybnaya Sloboda: 22+632 - 25+170 (Rybno-Slobodsky district)
Construction of stone mastics (grade 8) surface course. 08/25/2023 Аrsky Branch Kamenka – Dubyazy - Bolshaya Atnya: 42+385 - 43+079 (Atninsky district)
Strengthening of roadsides with M-400 macadam 08/25/2023 Menzelinsky Branch "Naberezhnye Chelny – Vodozabor" – Ilbukhtino- Kalmiya – "Menzelinsk – Biyurgan": 6+600 - 9+100 (Tukayevsky district)
Strengthening of roadsides with M-400 macadam, installation of bus stop and metal barriers. 08/24/2023 Аrsky Branch Koshar – Kliuchy-Sap: 7+500 - 7+990 (Atninsky district)
Construction works are finished. 08/23/2023 Menzelinsky Branch Road maintenance on local roads (Aktanyshsky district)
Summer road maintenance. 08/23/2023 Аrsky Branch Koshar – Kliuchy-Sap: 7+500 - 7+990 (Atninsky district)
Construction of stone mastics (grade 8, thickness 0.04 m) surface course. 08/22/2023 Apastovsky Branch August 22, 2023 P-241 Kazan – Ulyanovsk (Federal auto roads)
Summer road maintenance. 08/22/2023 Аrsky Branch M-7 "Volga" – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Construction of А32Нн porous coarse-grained asphaltic mix binder course 0.08m thick. 08/21/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: 0+043 - 2+489 (Arsky district)
Construction of А32Нн asphaltic mix binder course 8 cm thick. 08/21/2023 Menzelinsky Branch M-7 "Volga" (Federal auto roads)
Mowing the grass off with tractor-mounted mower. 08/21/2023 Apastovsky Branch Kazan – Ulyanovsk (Federal auto roads)
Reconstruction of worn-out asphaltic layers on "Kazan – Buinsk – Ulyanovsk" auto road in Apastovsky municipal district of the Republic of Tatarstan. 08/21/2023 Menzelinsky Branch "M-7 "Volga" – Konovalovka" – Staraya Ashpala: 0+000 - 2+860 (Menzelinsky district)
Workers of our company conduct stabilization of soil using regenerator-mixer. 08/18/2023 Menzelinsky Branch Almetyevsk – Musliumovo: 59+500 - 60+535; 64+975 - 65+590 (Musliumovsky district) Works are finished. 08/18/2023 Menzelinsky Branch Almetyevsk – Musliumovo: 55+500 - 59+500 (Musliumovsky district)
Works are finished. 08/17/2023 Apastovsky Branch Kazan – Ulyanovsk – Kamskoye Ustye: 43+779 - 44+854 (Kamsko-Ustyinsky district)
Strengthening of the roadsides with С-4 М-800 macadam-and-sand mix is finished. 08/17/2023 Apastovsky Branch Kazan – Ulyanovsk – Kamskoye Ustye: 44+854 - 46+054 (Kamsko-Ustyinsky district)
Strengthening of the roadsides with С-4 М-800 macadam-and-sand mix is finished. 08/17/2023 Apastovsky Branch “Kazan – Ulyanovsk” – Staroye Baryshevo - Kamskoye Ustye: 13+810 - 15+782 (Kamsko-Ustyinsky district)
Construction of А16Нн asphaltic mix levelling course and stone mastics surface course (grade 8) is finished. 08/17/2023 Apastovsky Branch Road network (macadam-and-sand mix) (Apastovsky district), 2023: 0+000 - 0+425; 0+000 - 0+150; 0+000 - 0+200; 0+000 - 0+500; 0+000 - 0+250; 0+000 - 0+120 (Apastovsky district)
Stabilization of soil with lime, construction of road surface course with macadam-and-sand mix (grade С-4 М-800). 08/16/2023 Apastovsky Branch Karatun – Cheremshan – Bolshoye Podberezye: 17+200 - 19+027 (Apastovsky district)
Construction levelling course is finished. 08/16/2023 Menzelinsky Branch "Aktanysh – Poisevo” – Bulyak: 9+920 - 16+020 (Aktanyshsky district)
Construction of А16Нн mix asphaltic levelling course is finished. 08/14/2023 Menzelinsky Branch "Naberezhnye Chelny – Vodozabor” – Ilbukhtino – Kalmya – “Menzelinsk - Biyurgan”: 6+600 - 9+100 (Tukayevsky district)
Construction of stone mastics surface course (grade 8). 08/14/2023 Mamadyshsky Branch Mamadysh – Kukmor: 9+900 - 12+000 (Mamadyshsky district)
Milling of the road surface. 08/14/2023 Mamadyshsky Branch М-7 "Volga" – Sekines, part Ragozino – Omarsky Pochinok: 0+000 - 3+085 (Mamadyshsky district)
Construction of stone mastics surface course (grade 8). 08/14/2023 Buinsky Branch Р-241 Kazan – Ulyanovsk (Federal auto roads)
Milling of the asphalted road surface, construction of pavement layers. 08/12/2023 Mamadyshsky Branch М-7 "Volga" (Federal auto roads)
Patching repair works on М-7 "Volga" federal auto road. 08/12/2023 Mamadyshsky Branch Road network (asphalt-concrete) (Mamadyshsky district), 2023: 0+000 - 0+520 (Mamadyshsky district)
Milling of the road network surface. 08/11/2023 Nizhnekamsky Branch Mira Avenue (from Vakhitov Avenue to Stroiteley Avenue): 0+000 - 1+986 (Nizhnekamsky district)
Milling of the asphalted road surface. 08/10/2023 Аrsky Branch Kamenka – Dubyazy – Bolshaya Atnya: 41+585 - 42+385 (Atninsky district)
Construction of 0.04 m thick stone mastics surface course (grade 8). 08/10/2023 Аrsky Branch Kamenka – Dubyazy – Bolshaya Atnya: 42+385 - 43+079 (Atninsky district)
Construction of 0.04 m thick stone mastics surface course (grade 8). 08/06/2023 Apastovsky Branch “Kazan – Ulyanovsk” – Staroye Baryshevo - Kamskoye Ustye: 5+020 - 5+970 (Apastovsky district)
Construction of stone mastics surface course (grade 8) is finished. 08/04/2023 Apastovsky Branch Road network (macadam-and-sand mix) (Kamsko-Ustyinsky district), 2023: 0+000 - 0+740; 0+000 - 0+140; 0+000 - 0+232; 0+000 - 0+300 (Kamsko-Ustyinsky district)
Construction of road surface course with macadam-and-sand mix (grade С-4 М-800). 08/04/2023 Аrsky Branch “Arsk – Bolshaya Atnya” - Koshlauch: 0+000 - 4+431 (Arsky district)
Stabilization of and strengthening of soil with lime. 08/04/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: 0+043 - 2+489 (Arsky district)
Construction of base course of macadam-and-sand mix (grade С-4 М800, thickness 25 cm). 08/03/2023 Аrsky Branch Bolshaya Atnya – Chepchugy: 0+483 - 0+603 (Atninsky district)
Construction of asphalt bedding course (А32Нн asphalt 0.08 m thick). 08/03/2023 Аrsky Branch M-7 “Volga” – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Construction of base course of macadam-and-sand mix (grade С-4 М800, thickness 30 cm).
08/03/2023 Аrsky Branch Kazan – Shemordan: 67+624 - 68+750; 64+975 - 65+575 (Tiulyachinsky district)
Construction of stone mastics surface course (grade 8). 08/03/2023 Buinsky Branch “Buinsk – Yalchiky” – Bik Uteyevo (Buinsky district)
Strengthening works on water pipes. Construction of 4 cm thick stone mastics surface course (grade 8). 08/03/2023 Аrsky Branch Kamenka – Dubyazy - Bolshaya Atnya: 41+585 - 42+385 (Atninsky district)
Construction of А16Нн asphaltic levelling course. 08/02/2023 Аrsky Branch Koshar – Kliuchy Sap: 7+500 - 7+990 (Atninsky district)
Construction of А16Нн asphaltic levelling course. 08/02/2023 Apastovsky Branch “Kazan – Ulyanovsk” – Kamskoye Ustye: 31+598 - 38+000 (Kamsko-Ustyinsky district)
Workers of our company conduct installation of metal barriers and strengthening of roadsides with macadam. 08/02/2023 Apastovsky Branch Road network (asphalt-concrete) (Verkhneuslonsky district), 2023: 0+000 - 0+601; 0+000 - 0+358 (Verkhneuslonsky district)
Construction of road surface course with asphalt-concrete mix (grade 5). 08/02/2023 Buinsky Branch “Staroye Drozhzhanoye – Tatarskiye Shatrashany” – Gorodishe (Drozhzhanovsky district)
Construction of 4 cm thick stone mastics surface course (grade 8). 08/02/2023 Menzelinsky Branch "Menzelinsk – Russkiy Karan – Togashevo” – Kuzembetyevo: 3+230 – 5+080 (Menzelinsky district) Construction of stone mastics (grade 8) surface course is finished.
08/02/2023 Menzelinsky Branch Musliumovo – Tatarskiy Shugan (Musliumovsky district) Application of vertical road marking on the drive way and installation of road signs is finished. 08/02/2023 Menzelinsky Branch Aktanysh – Musliumovo: 41+220 - 44+220 (Aktanyshsky district) Construction of stone mastics (grade 8) surface course. 08/01/2023 Suburban Branch Stolbistche – Atabayevo: 30+550 - 34+550 (Laishevsky district) Construction of auto road base course using cold regeneration method. Construction of sandy bedding course. 08/01/2023 Suburban Branch "Kazan – Orenburg” – Rybnaya Sloboda: 22+632 - 25+170 (Rybno-Slobodsky district) Construction of leveling course using А16Нт asphalt-concrete mix. 08/01/2023 Suburban Branch "Kazan – Orenburg” – Rybnaya Sloboda - Kornoukhovo: 0+000 - 10+880 (Rybno-Slobodsky district)
Construction of stone mastics (grade 8) surface course. 07/31/2023 Аrsky Branch Arsk – Mari El Republic limits: 0+000 - 1+488; 4+107 - 6+267 (Arsky district)
Construction of auto road surface course. 07/27/2023 Suburban Branch Maintenance works on local roads in Rybno-Slobodsky district of the Republic of Tatarstan (Rybno-Slobodsky district)
Reconstruction of worn-out asphalt-concrete layers on “M-7 “Volga” – Kutlu-Bukash – Rybnaya Sloboda” – Verkhniy Timerlek auto road. 07/27/2023 Аrsky Branch Tiubyak – Chekurcha – Yanga-Sala: 0+000 - 1+170 (Arsky district)
Works are finished. 07/26/2023 Apastovsky Branch Asphalt-concrete road network in Apastovsky district, 2023: 0+000 - 0+080; 0+000 - 0+110; 0+000 - 0+050 (Apastovsky district)
Workers of JSC “Tatavtodor” conduct construction of base course. 07/26/2023 Apastovsky Branch "Kazan – Ulyanovsk” – Staroye Baryshevo – Kamskoye Ustye: 13+810 - 15+782 (Kamsko-Ustyinsky district)
Widening of the road to match the grade. 07/25/2023 Apastovsky Branch Asphalt-concrete road network in Verkhneuslonsky district, 2023: 0+000 - 0+601; 0+000 - 0+358 (Verkhneuslonsky district)
Construction on levelling and surface courses of asphalt-concrete pavement. 07/24/2023 Аrsky Branch July 24, 2023 "Arsk – Bolshaya Atnya” – Koshlauch: 0+000 - 4+431 (Arsky district) Construction of subgrade. 07/24/2023 Menzelinsky Branch "Naberezhnye Chelny – Vodozabor” – Ilbukhtino-Kalmiya – Menzelinsk-Biyurgan: 6+600 - 9+100 (Tukayevsky district)
Construction of pavement widening trenches. Construction of А16Нн leveling course. 07/21/2023 Apastovsky Branch Macadam-and-sand road network in Apastovsky district, 2023: 0+000 - 0+425; 0+000 - 0+150; 0+000 - 0+200; 0+000 - 0+500; 0+000 - 0+250; 0+000 - 0+120 (Apastovsky district)
Stabilization of soil with lime is finished. 07/20/2023 Аrsky Branch Ashitbash – Shushmabash - Karaduvan: 0+043 - 2+489 (Arsky district)
Stabilization of soil with lime using regenerator-mixer. 07/20/2023 Аrsky Branch "Arsk – Bolshaya Atnya” – Koshlauch: 0+000 - 4+431 (Arsky district)
Construction of temporary bypass road pavement. 07/19/2023 Mamadyshsky Branch Mamadysh – Tiulyachi: 35+800 – 41+825 (Mamadyshsky branch)
Construction of surface course using stone mastics (grade 8). 07/19/2023 Mamadyshsky Branch Access road to Cattle breeding farm in Tavely inhabited locality: 0+000 - 9+911 (Mamadyshsky district)
Addition of complex binder to the soil. 07/19/2023 Apastovsky Branch "Kazan – Ulyanovsk" – Kamskoye Ustye: 31+598 - 38+000 (Kamsko-Ustyinsky district)
Construction of stone mastics (grade 8) road surface is finished. 07/18/2023 Apastovsky Branch "Kazan – Ulyanovsk" – Kamskoye Ustye: 43+779 - 44+854 (Kamsko-Ustyinsky district)
Construction of stone mastics (grade 8) road surface is finished. 07/17/2023 Suburban Branch М-7 "Volga" - Estachy: 0+000 - 4+653 (Vysokogorsky district)
Construction of surface course using stone mastics (grade 8). 07/16/2023 Apastovsky Branch "Kazan – Ulyanovsk" – Kamskoye Ustye: 44+854 - 46+054 (Kamsko-Ustyinsky district)
Construction of stone mastics (grade 8) road surface is finished. 07/14/2023 Apastovsky Branch "Kazan – Ulyanovsk" – Kamskoye Ustye: 31+598 - 38+000 (Kamsko-Ustyinsky district)
Workers of the company conduct construction of asphalted road base course (А32Нт asphalt-concrete mix). 07/14/2023 Aksubaevsky Branch Alekseyevskoye – Almetyevsk: 51+500 – 61+400 (Aksubayevsky district)
Construction of sub base of macadam, sand and gravel mix with addition of inorganic binder with active agent (M-60; h=0.22 m). 07/13/2023 Suburban Branch "Kazan - Orenburg" – settlement of 25 Oktyabrya collective farm - Aleksandrovsky: 0+000 - 5+453 (Laishevsky district)
Construction of sandy subsoil and macadam-and-sand base course (grade M-800 C-4). Construction of sub-base of А32Нн asphaltic mix and leveling course of А16Нн asphalt-concrete. 07/12/2023 Buinsky Branch "Kazan - Ulyanovsk" – Staroye Drozhzhanoye: 25+890 - 27+390 (Drozhzhanovsky district)
Workers of our company conduct construction of surface course of stone mastics (grade 8, thickness 4 cm) 07/10/2023 Nizhnekamsky Branch Access auto road to "Zarya" recreational camping: 0+000 - 1+985 (Nizhnekamsky district)
Construction of А16Вн top dressing. 07/10/2023 Sabinsky Branch "Kazan – Shemordan" – Pimery: 0+000 - 5+170 (Pestrechinsky district)
Workers of our company conduct construction of pavement. 07/06/2023 Buinsky Branch "Kazan - Ulyanovsk" – Staroye Drozhzhanoye: 34+520 - 35+820 (Drozhzhanovsky district)
Construction of leveling course and top dressing. 07/05/2023 Nizhnekamsky Branch Chistopol – Nizhnekamsk: 40+250 - 40+470; 66+818 - 68+698 (Nizhnekamsky district)
Construction of surface course using stone mastics (grade 16). 07/04/2023 Apastovsky Branch "Ulanovo – Karatun" – Bolshiye Kaibitsy: 23+400 - 27+318 (Kaibitsky district)
Construction of sub-base and surface course of asphalted surface is finished. 07/03/2023 Mamadyshsky Branch М-7 "Volga" - Usaly – Albay: 2+000 - 3+300; 4+700 - 5+400 (Mamadyshsky district)
Construction of surface course using stone mastics (grade 8). 07/01/2023 Menzelinsky Branch Local road maintenance in Menzelinsky district of the Republic of Tatarstan (Menzelinsky district) 07/01/2023 Apastovsky Branch Local road maintenance in Verkhneuslonsky district of the Republic of Tatarstan (Verkhneuslonsky district) 07/01/2023 Menzelinsky Branch Local road maintenance in Musliumovsky district of the Republic of Tatarstan (Musliumovsky district) 07/01/2023 Mamadyshsky Branch Mamadysh – Tiulyachi: 35+800 - 41+825 (Mamadyshsky district)
Construction of solid concrete edge drain. 07/01/2023 Mamadyshsky Branch М-7 "Volga" - Usaly – Albay: 2+000 - 3+300; 4+700 - 5+400 (Mamadyshsky district)
Strengthening of roadsides with M-400 macadam. 07/01/2023 Mamadyshsky Branch Mamadysh – Kukmor: 9+900 - 12+000 (Mamadyshsky district)
Strengthening of roadsides with M-400 macadam. 07/01/2023 Menzelinsky Branch М-7 "Volga" – Novaya Aleksandrovka – Tulubayevo: 13+460 - 15+710 (Menzelinsky district)
Workers of our company conduct construction of additional sandy base course and sub-base of cemented sand-and-gravel mix. 07/01/2023 Menzelinsky Branch Musliumovo – Tatarskiy Shugan (Musliumovsky district)
Construction of surface course using stone mastics (grade 8), strengthening of roadsides with M-400 macadam. 07/01/2023 Menzelinsky Branch Aktanysh – Musliumovo: 41+220 - 44+220 (Aktanyshsky district)
Construction of leveling course of А16Нн asphaltic mix is finished. 06/30/2023 Apastovsky Branch "Kazan – Ulyanovsk" – Staroye Baryshevo – Kamskoye Ustye: 5+020 - 5+970 (Apastovsky district)
Workers conduct construction of leveling course of А16Нн asphaltic mix. 06/30/2023 Suburban Branch "Kazan – Orenburg" – Rybnaya Sloboda: 15+258 - 16+858 (Rybno-Slobodsky district)
Works are finished. 06/29/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: 0+043 - 2+489 (Arsky district)
Excavation works in soils of second category: cutting of the earth fill. 06/29/2023 Аrsky Branch "Kazan – Shemordan" - Lesnoy: 9+090 - 13+275 (Tiulyachinsky district)
Milling of old road surface, loading of the removed surface into the dump trucks. 06/29/2023 Apastovsky Branch "Kazan – Ulyanovsk" – Kamskoye Ustye: 31+598 - 38+000 (Kamsko-Ustyinsky district)
Stabilization of soil with lime and construction of base course of C-4 M-800 macadam-and-sand mix. 06/27/2023 Suburban Branch Maintenance works on local roads in Rybno-Slobodsky district of the Republic of Tatarstan (Rybno-Slobodsky district)
Summer auto road maintenance works. 06/26/2023 Аrsky Branch Kazan – Shemordan: 78+700 - 81+678 (Tiulyachinsky district)
Construction of surface course of stone mastics (grade 16, thickness 0,05 m) 06/24/2023 Аrsky Branch М-7 "Voga" - Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Construction of sandy subsoil 0.20 m thick. 06/23/2023 Suburban Branch М-7 "Volga" - Estachy: 0+000 - 4+653 (Vysokogorsky district) Construction of sandy subsoil and C-4 macadam-and-sand base course on exit roads. 06/23/2023 Аrsky Branch Arsk – Mari El Republic limits: 1+488 - 4+107 (Arsky district)
Construction of auto road surface course. 06/23/2023 Apastovsky Branch Access road to Yambulatovo village (Verkhneuslonsky district)
Strengthening of roadsides with M-400 macadam is finished. 06/23/2023 Apastovsky Branch "Ulanovo – Karatun" – Bolshiye Kaibitsy: 23+400 - 27+318 (Kaibitsky district)
Construction of base course of C-4 M-800 macadam-and-sand mix. 06/23/2023 Аrsky Branch М-7 "Volga" – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Construction of reinforced concrete pipe. 06/23/2023 Aksubaevsky Branch Chistopol – Aksubayevo – Nurlat: 41+650 – 46+075 (Aksubayevsky district)
Construction of surface course using stone mastics (grade 8). 06/23/2023 Suburban Branch "Kazan – Orenburg" – Rybnaya Sloboda - Kornoukhovo: 0+000 - 10+880 (Rybno-Slobodsky district)
Construction of sandy subsoil. 06/22/2023 Mamadyshsky Branch Access road to Cattle breeding farm in Tavely inhabited locality: 0+000 - 9+911 (Mamadyshsky district)
Construction of corrugated water pipes. 06/22/2023 Аrsky Branch М-7 "Volga" – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Stabilization of soil with lime. 06/21/2023 Suburban Branch Kazan – Shemordan: 25+224 - 25+787; 26+793 - 29+780 (Pestrechinsky district)
Construction of surface course using stone mastics (grade 8 and 16). 06/21/2023 Аrsky Branch М-7 "Volga" – Balandysh: 6+723 - 10+000 (Tiulyachinsky district)
Construction of earth bed. 06/21/2023 Аrsky Branch Kazan – Shemordan: 78+700 - 81+678 (Tiulyachinsky district)
Construction of asphalt-concrete leveling course. 06/20/2023 Mamadyshsky Branch Access road to Cattle breeding farm in Tavely inhabited locality: 0+000 - 9+911 (Mamadyshsky district)
Construction of reinforced concrete water pipes. 06/20/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: 0+043 - 2+489 (Arsky district)
Construction of sub-base using cold regeneration method with addition of M-800 macadam. 06/20/2023 Suburban Branch "Kazan - Orenburg" – settlement of 25 Oktyabrya collective farm - Aleksandrovsky: 0+000 - 5+453 (Laishevsky district)
Construction of sub-base using cold regeneration method with addition of M-800 macadam, portland cement and water. 06/20/2023 Аrsky Branch Kazan – Shemordan: 65+575 - 67+624 (Tiulyachinsky district)
Strengthening of roadsides. 06/20/2023 Аrsky Branch Tiubyak – Checkurcha – Yanga-Sala: 0+000 - 1+170 (Arsky district)
Strengthening of roadsides with M-400 macadam. 06/16/2023 Aksubaevsky Branch Alekseyevskoye – Almetyevsk: 51+500 - 61+400 (Aksubayevsky district) Workers of JSC “Tatavtodor” conduct pavement construction. 06/16/2023 Buinsky Branch Russkiye Kischaky – Koshky-Novotimbayevo: 0+000 - 3+874 (Buinsky district)
Strengthening of roadside ditches with RENO gabion mattresses. 06/16/2023 Buinsky Branch Apastovo – Tetiushi: 9+802 - 11+902 (Tetiushsky district)
Construction of leveling course of А16Нн asphaltic mix is in process. 06/16/2023 Mamadyshsky Branch Maintenance works on local roads in Mamadyshsky district of the Republic of Tatarstan (Mamadyshsky district)
Reconstruction of worn-out layers of asphalted surfaces using porous-mastic asphalt-concrete mixes. 06/16/2023 Mamadyshsky Branch "М-7 "Volga" – Sekines – Omary: 0+000 - 3+822 (Mamadyshsky district) Installation of pipes for road signs. 06/16/2023 Mamadyshsky Branch Maintenance works on local roads in Mamadyshsky district of the Republic of Tatarstan (Mamadyshsky district) 06/16/2023 Menzelinsky Branch Maintenance works on local roads in Aktanyshsky district of the Republic of Tatarstan (Aktanyshsky district) 06/15/2023 Apastovsky Branch "Kazan - Ulyanovsk" – Kamskoye Ustye: 31+598 - 38+000 (Kamsko-Ustyinsky district)
Soil stabilization works in progress. 06/15/2023 Nizhnekamsky Branch Chistopol – Nizhnekamsk: 75+923 - 78+923 (Nizhnekamsky district)
Construction of surface course with stone mastics (grade 16). 06/14/2023 Aksubaevsky Branch Alekseyevskoye – Almetyevsk: 51+500 - 61+400 (Aksubayevsky district)
Construction of sand-and-gravel base course, with addition of inorganic binder with M-60 active agent. 06/14/2023 Menzelinsky Branch Almetyevsk – Musliumovo: 55+500 - 59+500 (Musliumovsky district)
Construction of levelling course (А16Нн asphaltic mix) and surface course (stone mastics grade 8) is finished. 06/13/2023 Nizhnekamsky Branch Chistopol – Nizhnekamsk: 61+173 - 65+656 (Nizhnekamsky district)
Construction of surface course with stone mastics (grade 16). 06/09/2023 Apastovsky Branch "Ulanovo – Karatun" – Bolshiye Kaibitsy: 23+400 - 27+318 (Kaibitsky district) Construction of roadbed in progress. 06/09/2023 Sabinsky Branch "Kazan - Shemordan" – Pimery: 0+000 - 5+170 (Pestrechinsky district)
Construction of 20 cm thick roadbed using M-800 macadam-and sand mix. 06/09/2023 Menzelinsky Branch М-7 "Volga" – Novaya Aleksandrovka - Tulubayevo: 13+460 - 15+710 (Menzelinsky district)
Stabilization of soil using regenerator-mixer. 06/09/2023 Suburban Branch Kamenka – Dubyazy – Bolshaya Atnya: 19+965 - 22+265 (Vysokogorsky district)
Works are finished. 06/09/2023 Menzelinsky Branch "Menzelinsk – Russkiy Karan – Togashevo” – Kuzembetyevo: 1+030 - 3+230 (Menzelinsky district)
Stabilization of roadsides with macadam is finished. 06/09/2023 Menzelinsky Branch Aktanysh – Musliumovo – settlement of Kirov collective farm: 4+580 - 7+080 (Aktanyshsky district)
Construction of levelling course (А16Нн asphaltic mix) and surface course (stone mastics grade 8), strengthening of roadsides with macadam. 06/08/2023 Suburban Branch Stolbistche – Atabayevo: 3+830 - 4+930 (Laishevsky district)
Works are finished. 06/07/2023 Apastovsky Branch "Kazan - Ulyanovsk" – Kamskoye Ustye: 44+854 - 46+054 (Kamsko-Ustyinsky district)
Construction of levelling course (А16Нн asphaltic mix) in progress. 06/06/2023 Apastovsky Branch Bolshiye Kaibitsy - Bagayevo: 1+440 - 2+440 (Kaibitsky district)
Construction of roadsides with M-400 macadam is finished. 06/06/2023 Apastovsky Branch "Kazan - Ulyanovsk" – Kamskoye Ustye: 31+598 - 38+000 (Kamsko-Ustyinsky district)
Soil stabilization with lime. 06/05/2023 Apastovsky Branch "Kazan - Ulyanovsk" – Kamskoye Ustye: 43+779 - 44+854 (Kamsko-Ustyinsky district)
Construction of levelling course (А16Нн asphaltic mix) in progress. 06/05/2023 Apastovsky Branch Access road to Yambulatovo village (Verkhneuslonsky district)
Construction of surface course with stone mastics (grade 8) is finished. 06/03/2023 Apastovsky Branch "Ulanovo – Karatun" – Bolshiye Kaibitsy: 23+400 - 27+318 (Kaibitsky district)
Workers of JSC “Tatavtodor” conduct stabilization and strengthening of soil using regenerator. 06/02/2023 Apastovsky Branch Karatun – Cheremshan – Bolshoye Podberezye: 0+000 - 1+100 (Apastovsky district)
Reinforcement of road with sub-base is finished. 06/02/2023 Buinsky Branch "Kazan – Ulyanovsk” – Confectionery factory”: 1+100 - 1+140 (Buinsky district)
Construction of sub-base and surface course of asphalted road, surfacing of sidewalks, strengthening of roadsides with M-400 macadam. 06/02/2023 Apastovsky Branch "Kazan - Ulyanovsk" – Kamskoye Ustye: 43+779 - 44+854 (Kamsko-Ustyinsky district)
Milling of the road surface in progress. 06/01/2023 Аrsky Branch Kazan- Shemordan: 68+750 - 70+088 (Tiulyachinsky district)
Construction of surface course with stone mastics (grade 8). 06/01/2023 Buinsky Branch "Staroye Drozhzhanoye – Tatarskiye Shatrashany" – Gorodistche (Drozhzhanovsky district)
Construction of 6 cm thick asphalt-concrete base course on exit roads. 05/30/2023 Suburban Branch "Rybnaya Sloboda – Yanchikovo” – Malyi Atmas: 0+000 - 3+733 (Rybno-Slobodsky district)
Strengthening of enriched sand-and-gravel mix road base with cement. Construction of sub-base with А32Нн asphalt-concrete mix. 05/30/2023 Suburban Branch "Kazan – Orenburg” – Rybnaya Sloboda: km 15+258 – km 16+858 (Rybno-Slobodsky district) Construction of А16Нт asphaltic mix levelling course. Construction of surface course with stone mastics (grade 8). 05/30/2023 Suburban Branch "Kazan – Orenburg”- settlement of 25 Oktyabrya state farm - Aleksandrovsky: km 0+000 – km 5+453 (Laishevsky district)
Construction of earthen roadbed, construction of base course using cold recycling method (1st pass). 05/29/2023 Apastovsky Branch Road maintenance works on local roads in Verkhneuslonsky district of the Republic of Tatarstan (Verkhneuslonsky district) 05/29/2023 Аrsky Branch Kazan – Shemordan: km 65+575 – km 67+624 (Tiulyachinsky district)
Construction of surface course with stone mastics (grade 8). 05/29/2023 Аrsky Branch Kazan – Shemordan: km 65+575 – km 67+624 (Tiulyachinsky district)
Construction of А16Нт asphaltic mix levelling course. 05/29/2023 Аrsky Branch Kazan – Shemordan: km 68+750 – km 70+088 (Tiulyachinsky district)
Construction of levelling course. 05/29/2023 Apastovsky Branch 05/29/2023 Apastovsky Branch Bolshiye Kaibitsy – Bagayevo: km 1+440 – km 2+440 (Kaibitsky district)
Workers of our company conduct construction of surface course with stone mastics (grade 8). 05/29/2023 Apastovsky Branch Karatun – Cheremshan – Bolshoye Podberezye: km 0+000 – km 1+100 (Apastovsky district)
Improvement of road parts. 05/27/2023 Аrsky Branch Road maintenance works on local roads in Arsky district of the Republic of Tatarstan (Arsky district)
Grass mowing with rubber-tyred tractor mower. 05/27/2023 Apastovsky Branch Access road to Yambulatovo village (Verkhneuslonsky district)
Construction of А16Нн asphaltic mix levelling course is finished. 05/26/2023 Аrsky Branch Kazan – Shemordan: km 68+750 – km 70+088 (Tiulyachinsky district)
Milling of old asphaltic surface. 05/26/2023 Buinsky Branch "Staroye Drozhzhanoye – Tatarskiye Shatrashany” – Gorodische (Drozhzhanovsky district)
Construction of sandy base course (20 cm) and macadam-and-sand subgrade (20 cm, grade С4 М800) on access tracks. 05/26/2023 Apastovsky Branch Road maintenance works on local roads in Verkhneuslonsky district of the Republic of Tatarstan (Verkhneuslonsky district)
Patching of asphaltic surface is finished. 05/26/2023 Aksubaevsky Branch Chistopol – Aksubayevo – Nurlat: km 77+957 – km 79+457 (Aksubayevsky district)
Construction of asphalt surface course of stone mastics (grade 8). 05/25/2023 Аrsky Branch Ashitbash – Shushmabash – Karaduvan: km 0+043 – km 2+489 (Arsky district)
Milling of asphalted surface. 05/23/2023 Suburban Branch Kamenka – Dubyazy – Bolshaya Atnya: km 19+965 – km 22+265 (Vysokogorsky district)
Construction of А16Нн asphaltic mix levelling course. Construction of surface course with stone mastics (grade 8). 05/19/2023 Aksubaevsky Branch Chistopol – Aksubayevo – Nurlat: km 41+650 – km 46+075 (Aksubayevsky district)
Construction of levelling course with А16Нт asphalt-concrete mix. 05/18/2023 Nizhnekamsky Branch Naberezhnye Chelny – Zayinsk – Almetyevsk – Nizhnekamsk: km 2+900 – km 3+900 (Tukayevsky district)
Construction of asphalt surface course of stone mastics (grade 16). 05/18/2023 Apastovsky Branch Maintenance works on local roads in Kamsko-Ustyinsky district (Kamsko-Ustyinsky district) 05/17/2023 Аrsky Branch Tiubyak – Chekurcha – Yanga-Sala: km 0+000 - km 1+170 (Arsky district)
Construction of asphalt surface course of stone mastics (grade 8, 0.04 m thick). 05/17/2023 Apastovsky Branch Road network in Apastovo township: 0+000 - 0+481; 0+000 - 0+716; 0+000 - 0+524; 0+000 - 0+151; 0+000 - 0+209 (Apastovsky district)
Construction of subbase of hot А32Нн asphaltic mix on A. Alisha Street is finished. 05/17/2023 Аrsky Branch Tiubyak – Chekurcha – Yanga-Sala: km 0+000 - km 1+170 (Arsky district) Construction of levelling course. 05/16/2023 Apastovsky Branch Access road to Pobeda village: km 0+000 – km 2+120 (Kaibitsky district)
Stabilization and strengthening of soil with regenerator-mixer with addition of lime. 05/16/2023 Аrsky Branch М-7 "Volga” – Balandysh: km 6+723 – km 10+000 (Tiulyachinsky district)
Construction of temporary bypass road for the period of full reconstruction of the auto road. 05/16/2023 Аrsky Branch Kazan – Shemordan: km 78+700 – km 81+678 (Tiulyachinsky district)
Milling of asphalted surface. 05/16/2023 Menzelinsky Branch "Menzelinsk – Russkiy Karan – Togashevo” – Kuzembetyevo: km 1+030 – km 3+230 (Menzelinsky district)
Construction of levelling course with А16Нн asphalt-concrete mix, construction of asphalt surface course of stone mastics (grade 8). 05/15/2023 Apastovsky Branch Bolshiye Kaybitsy – Bagayevo: km 1+440 – km 2+441 (Kaibitsky district)
Construction of levelling course with А16Нн asphalt-concrete mix is finished. 05/15/2023 Buinsky Branch Maintenance works on local roads in Drozhzhanovsky district of the Republic of Tatarstan (Drozhzhanovsky district)
Patching repair on public roads. 05/15/2023 Аrsky Branch Maintenance works on local roads in Tiulyachinsky district of the Republic of Tatarstan (Tiulyachinsky district) 05/13/2023 Apastovsky Branch Kazan – Ulyanovsk – Kamskoye Ustye: km 43+854 – km 44+854 (Kamsko-Ustyinsky district)
Widening of the base course to match the grade. 05/13/2023 Apastovsky Branch Access road to Yambulatovo village (Verkhneuslonsky district) Patching repair is finished. 05/12/2023 Suburban Branch Kazan – Shemordan: km 25+224 – km 25+787; km 26+793 – km 29+780 (Pestrechinsky district)
Cold milling of asphalted surface. Construction of levelling course with А16Нн asphalt-concrete mix. 05/12/2023 Suburban Branch Kazan – Shemordan: km 33+440 – km 35+100 (Pestrechinsky district)
Cold milling of asphalted surface. Construction of levelling course with А16Нн asphalt-concrete mix. 05/12/2023 Suburban Branch "Kazan – Orenburg” – Rybnaya Sloboda: km 15+258 – km 16+858 (Rybno-Slobodsky district)
Cold milling of asphalted surface. 05/11/2023 Apastovsky Branch Road network in Apastovo township: 0+000 - 0+481; 0+000 - 0+716; 0+000 - 0+524; 0+000 - 0+151; 0+000 - 0+209 (Apastovsky district)
Construction of А32Нн base course and surface course of stone mastics (grade 8) is finished. 05/11/2023 Buinsky Branch Russkiye Kischaky – Koshky – Novotimbayevo: km 0+000 - km 3+874 (Buinsky district)
Soil compacting for subsurface drainage with excavator-mounted hydraulic vibratory tamper. 05/05/2023 Apastovsky Branch Road network in Apastovo township: 0+000 - 0+481; 0+000 - 0+716; 0+000 - 0+524; 0+000 - 0+151; 0+000 - 0+209 (Apastovsky district)
Construction of levelling base course with С4 М-800 macadam-and-sand mix. 05/05/2023 Sabinsky Branch “Kazan – Shemordan” - Pimery: km 0+000 – km 5+170 (Pestrechinsky district)
Construction of earth roadbed. 05/05/2023 Mamadyshsky Branch М-7 "Volga" – Sekines, part Ragozino – Omarskiy Pochinok: km 0+000 – km 3+085 (Mamadyshsky district) Excavation works in progress. 05/04/2023 Apastovsky Branch
Kazan – Ulyanovsk – Kamskoye Ustye: km 31+598 – km 38+000 (Kamsko-Ustyinsky district) Breaking of road surface.
05/03/2023 Nizhnekamsky Branch Vakhitova Ave. (from Sobilekovskaya Street to Khimikov Ave. roundabout – to Vakhitov Ave.): km 0+000 – km 1+465 (Nizhnekamsky district)
Cold milling of asphaltic surface.
05/03/2023 Apastovsky Branch |